I need to change the runtime of my valves/bays in a schedule, how can I do that?
Answer
You can edit the item from the Schedule Editor by clicking on the item you need, making the changes in the pop-up window and saving your changes.
Overview
If the schedule hasn't started yet, go to 'Scheduled' from the Schedule Overview on your desktop, (if schedule has already started see this article), click on the relevant schedule and click Edit. In the Schedule Editor, click on the item you need and you'll be able to change the settings:
Click Save when you're happy with your changes.